Hong Kong Disneyland Resort Line (DRL)

Project Overview
     From urbantransport-technology.com  

Contract Nature Companies
Environmental Impact Assessment (EIA)
Environmental Resources Management (ERM) Hong Kong Ltd
     Reference from Government
Consultant
Ove Arup & Partners Hong Kong Ltd
     Reference from Arup
Independent Checking Engineer (ICE)
Atkins China Limited
     Reference from Atkins
Contractor - Sunny Bay Station (contract number 580)
Maeda Corporation
Design and Construction Contractor - Tai Yam Teng Tunnel (contract number 581)
Gammon Construction Limited
     Reference from Gammon
Contractor - Disney Station (contract number 583)
Gammon Construction Limited
     Reference from Gammon

Remarks

Artist illustration of Penny's Bay Station

Related Projects

Hong Kong Disneyland